PCBA VALIDATION

#30872

PCBA VALIDATION | 6 October, 2004

We will be outsourcing all of our PCBAs and would like to know if other companies perform DVT testing, ESD, Emissions on all of your boards or only on main boards? Our shipping deadline is near and I would like to determine the risk in not performing any testing on our boards and only visualy inspecting them. The PCBA contract manufacturer has build most of our other boards and we have never had a problem. I appreciate your help and response. Thank you.

reply »

#30927

PCBA VALIDATION | 12 October, 2004

We do not outsource assembly of our product, but we have discussed it. So, until other fine folk at SMTnet respond, we thought we�d rattle on for a while and maybe inspire some other chatter on the topic.

As we understand it, you: * Currently contract your board assembly. * Assemble, test, and verify performance of the product. * Plan to contract all board assembly and product assembly, test, and performance verification. * Would like to understand the risk in not performing any testing on our boards and only visually inspecting them.

The plan to visual inspect ONLY sounds risky enough to us that we suggest an interim program of verification. * We assume you�re comfortable with your supplier�s capabilities in the area where the responsibilities are changing. * We assume the contract requires your supplier to perform DVT testing, ESD, emissions, and whatnot prior to shipment to your plant. * We�d suggest that you sample shipments from your supplier for verification, in addition to the visual inspection that you mentioned. We�d expect that you�d reduce the sample size as your supplier�s performance continues to meet expectations.

reply »

Visagan

#30994

PCBA VALIDATION | 17 October, 2004

We are PCBA manufacturers with all capabilities such as SMt, AI & PWB with AOI, ICT testing facilities. If you are interested in outsourcing your job pl contact visagan@texmaco.co.id

reply »

joe

#31081

EMS Provider | 25 October, 2004

> We will be outsourcing all of our PCBAs and would > like to know if other companies perform DVT > testing, ESD, Emissions on all of your boards or > only on main boards? Our shipping deadline is > near and I would like to determine the risk in > not performing any testing on our boards and only > visualy inspecting them. The PCBA contract > manufacturer has build most of our other boards > and we have never had a problem. I appreciate > your help and response. Thank you.

DBG established in April,1995,awarded ISO9001 & QS9000 by TUV,is one of leading China EMS manufacturers providing manufacturing solutions to the world��s companies,Our services focus on PCBA subcontracting and value-added assembly.

Pls visit http://www.dbg.com.cn to get more information Email:market2@dbg.com.cn joeyangrong@yahoo.com

reply »

#31113

PCBA VALIDATION | 27 October, 2004

I would strongly suggest you run a qualification test program on all your boards to verify the design and the manufacturing processes. Only visual inspection seems pretty risky approach, even if the boards were produced in-house.

reply »