Key Production Indicators

Mark S.

#20748

Key Production Indicators | 18 July, 2002

As part of our Efficiency Improvement Plan I have been tasked at determining the Key Production Indicators from available production data. So I thought I would ask others what they thought were 1) the top production indicators for their facilites 2) how they captured/reported this information 3) how they planned an improvement plan using these indicators.

This message was posted via the Electronics Forum @

reply »

#20750

Key Production Indicators | 18 July, 2002

Universal Instruments charts five barriers to success 1. Nonconforming material reports 2. Parts shortages 3. Configuration changes 4. Miscellaneous - rework, software changes 5. Assembly errors

reply »

#20764

Key Production Indicators | 18 July, 2002

Machine efficiency is a big one. Placement and auto-insertion machines should have the production rate for a given product recorded in the Routing, Time Standard or Work Instruction. If a given board has a tact time of say 1 minute and you ran 1,000 boards then at 100% efficiency the production time should be 1,000 minutes. Record what you?re actually achieving and break down reasons why you had machine stoppage. Make Pareto charts to attack the most frequent reasons for machine stoppage. This efficiency system should be applied to all assembly operations in the plant. Time standards must always be reviewed, evaluated and measured for improvement.

reply »

Mark Susol

#20774

Key Production Indicators | 18 July, 2002

Well I'm sure I'm not the only who has this experience but even when things are going really well..you never realize 100% of what the machine says you SHOULD be able to do.

So what I look at is the labor start time & stop time of the WO and the total machine placements of the job. So I'm able to draw a baseline after a couple runs for Product X. I end up with something like 6,000 PPHR on a job that the machine says we should be getting 10,000 PPPHR. The machine theoretical PPPHR over several jobs otpimized is very misleading...IMO. If I ran one product nonstop I think it would more useful.

Over time I'm seeing this value increase for each product. This does seem like a key indicator as it isn't effected by schedule loading, material planning issues etc.

I have a hard time getting the machine stats to agree with the labor stats. I feel like an Army Recruiter sold us our machine, sure it will do "x" pphr...just didn't define what an hour meant.

reply »

#20780

Key Production Indicators | 18 July, 2002

Forget what the machine's max. placement cycle rate is spec'd for. For each board you assemble time the actual placement rate. To do this start the stop watch the instant the camera is positioned over the first fiducial on the first board, then stop the watch the instant the camera is positioned over the first fiducial on the second board. That's the "actual tact time" for that given board and factors in board load/unload time. Be sure that the placement cycle had no "pick recovery"- meaning it was a continuous placement cycle with no stopping and no "miss-picks". If you have multiple placement machines in the line, your slowest tact time machine is the actual for the line. Then you'll have to burden the actual tact time for machine stoppage. Stoppage for feeder changeovers, operator issues, machine malfunctions,..... List all the reasons you are seeing stoppage on the machine(s). You're goal is to achieve the best against the measured tact time. Record machine stoppages during the job and break them down by categories and work to stop the stoppage! Correct stoppage issues that are within your control. Account for stoppage issues that are not in your control, such as defective components being rejected by the vision system. Record this down time and report issues to the supplier and get relief ($$) on your next purchase. The same goes for PWBs. The percentage of the actual tact time is what you want to be concerned about. This is your measure of efficiency. If you follow the continuous flow mfg. principle- which is that you do not start a job unless you have all the components to complete the job and once you start the job you do not stop until its complete- running out of material is not a factor. If you follow the machine OEM's preventative maintenance schedules to keep your machines in "tip top condition", then unscheduled machine down time should be minimal. If your machine stops for feeders empty and your method is to re-load the same feeder, this is the greatest time consumer and it is difficult to establish a standard. Having extra feeders loaded and in close proximity to the machine makes a time standard possible. Loading a feeder onto the machine is a standard time vs. loading a component onto a feeder then loading a feeder onto the machine is a variable time. The investment for extra feeders may be justified if you can show how much more product you can build (generate revenue) in a given time period. FYI: Some machines are smart enough not to stop the placement cycle for empty feeders and can have feeders removed and installed while the machine is cycling. Set up time is another measure of efficiency. 15 - 20 minutes is standard for efficient companies. Look to create procedures and configure your line to achieve a standard time for setup. My instructions to the SMT line super. was to maintain 75-85% of actual tact time and to be placing boards for job "B" by the time job "A"'s last board came out of the oven. This was with 2 lines of Fuji, each w/ GSP2, CP3, CP3, IP2, and Vitronics SMR1100. But then again, I've been called a ball buster.

reply »

Mark S.

#20812

Key Production Indicators | 22 July, 2002

>> Set up time is another measure of efficiency. 15 - 20 minutes is standard for efficient companies.<<

So then how are you measuring this? Are you measuring it directly or taking the total shift time minus the hours the operators/machines indicated they were operating?

My crew will setup 3-4 jobs offline to about 80% completion then we changed tables/feeders etc. and then continue operating from there. I'm only concerned with the amount of time the mahcine isn't actually running.

This message was posted via the Electronics Forum @

reply »

#20928

Key Production Indicators | 29 July, 2002

From the time the last board from "Job A" exits the oven until the first board from "Job B" exits the oven.

reply »